Risk Assessment — NexavionERP
Assets/Risk Assessment
Ana Kowalski
ana@meridianco.com
Log Out

Risk Assessment

RA-014 is the assessment for the OLT card job. Residual risk is what remains after the controls.

Active Risk Assessments28
RA-014 is the OLT job
High Residual Risks3
RA-030 is still High
Reviews Due4
RA-014 was brought forward
Risk register
RA-014 starts High and finishes Medium once the controls are in place. Those controls are the permit conditions.
0 selected
Risk IDActivityLocationJob RoleHazardLikelihoodSeverityInitial RiskControlsResidual RiskReview DateStatus
RA-014OLT card replacementKingston Head-EndFibre TechnicianElectrical energy34HighIsolate the DC breaker, insulated gloves, eye protection, electrical permitMedium01 Dec 2026Active
RA-018Generator serviceMontego Bay POPPlant TechnicianHot surface, fuel24HighCool-down, fuel shut-off, hot-work permitMedium15 Jan 2027Active
RA-022Battery replacementMandeville POPPlant TechnicianElectrolyte23MediumFace shield, gloves, eyewashLow20 Oct 2026Due
RA-026Span workSpanish TownFibre TechnicianWorking at height34HighHarness, second person, permitMedium01 Nov 2026Active
RA-030ExcavationPortmoreCivil crewUnderground services25HighScan, permit, hand digHigh01 Feb 2027Active
Controls
CTRL-014 is the control set behind RA-014, SP-014 and PTW-014.
Control IDRiskHazardControl MeasureControl TypeOwnerVerificationEffectivenessStatus
CTRL-014RA-014Electrical energyIsolate the DC breaker, insulated gloves, eye protection, electrical permitIsolation and PPEOR Omar ReidPermit and briefingResidual MediumActive
CTRL-018RA-018Hot surface, fuelCool-down, fuel shut-off, hot-work permitProcedure and permitOR Omar ReidPermit PTW-018Residual MediumActive
CTRL-022RA-022ElectrolyteFace shield, gloves, eyewashPPEAP Andre PowellPPE issueResidual LowActive
CTRL-026RA-026Working at heightHarness, second person, permitPPE and permitKM Keisha MorganBriefing BRF-022Residual MediumActive
CTRL-030RA-030Underground servicesScan, permit, hand digProcedureLC Leroy CampbellPermit refusedResidual HighActive
Point of work
The controls presented on WO-4414 are the RA-014 controls, not a second list.
Risk AssessmentJob PlanPermitWork OrderAssetLocationControls PresentedWorker AcknowledgementStatus
RA-014JP-014PTW-014WO-4414AST-OLT-014Kingston Head-EndIsolate the DC breaker, insulated gloves, eye protection, electrical permitKeisha Morgan, 05 Oct 2026 07:55Active
RA-018JP-088PTW-018WO-4419AST-GEN-014Montego Bay POPCool-down, fuel shut-off, hot-work permitWaiting on BRF-018Pending
RA-022JP-026PTW-022—AST-BAT-014Mandeville POPFace shield, gloves, eyewashWaitingPending
RA-026JP-030PTW-026—AST-FBR-014Spanish TownHarness, second person, permitKeisha Morgan, 04 Oct 2026 06:40Active
RA-030—PTW-030—Portmore ductPortmoreScan, permit, hand digPermit rejectedOpen
Review schedule
RA-014 is on a six-month review. RA-022 was pulled forward because the battery activity changed.
Risk AssessmentReview IntervalLast ReviewNext ReviewActivity ChangedControl ChangedReview TriggerReviewerStatus
RA-0146 months01 Jun 202601 Dec 2026NoNoScheduled ReviewOR Omar ReidActive
RA-0146 months01 Jun 202620 Oct 2026NoYes, after INC-014IncidentOR Omar ReidDue
RA-02212 months20 Oct 202520 Oct 2026YesNoActivity ChangeAP Andre PowellDue
RA-01812 months15 Jan 202615 Jan 2027NoNoScheduled ReviewOR Omar ReidActive
RA-0266 months01 May 202601 Nov 2026NoYesControl ChangeKM Keisha MorganActive

Initial risk High, from likelihood 3 and severity 4. After Isolate the DC breaker, insulated gloves, eye protection, electrical permit, residual risk is Medium.

Machine-generated score agrees with the High initial rating. Human approval required on the permit. The score does not change the rating.

Isolate the DC breaker, insulated gloves, eye protection, electrical permit

Presented at the briefing and on the permit: Isolate the DC breaker, insulated gloves, eye protection, electrical permit.

INC-014 brought the next review forward to 20 Oct 2026 because the control set changed.

Nexavion AI● Online