Project Setup
Initiate projects with budget, team and billing structure. Committed budgets on the three live build projects are JMD 100,000,000 + 18,000,000 + 24,000,000.
Active Projects18
Working set below, plus 12 more
Budget CommittedJMD 142,000,000
PRJ-14, PRJ-18 and PRJ-22
Projects at Funding Cap2
PRJ-26 and PRJ-33
Active Projects
Recently created and in-flight projects
| Project ID | Name | Client | Budget | PM | Status |
|---|---|---|---|---|---|
| PRJ-1066 | Orion Expansion | Northwind Traders | $920,000 | Sofia Okafor | Awaiting Kickoff |
| PRJ-1064 | Falcon Pilot | Umbra Health Group | $340,000 | David Kim | Awaiting Kickoff |
| PRJ-1058 | Meridian Refit | Internal | $860,000 | Elena Torres | On Track |
| PRJ-1047 | Atlas Migration | Northwind Traders | $1,680,000 | Sofia Okafor | At Risk |
| PRJ-1052 | Helios Rollout | Bluepeak Energy | $2,400,000 | Julian Reyes | On Track |
| PRJ-1061 | Beacon Upgrade | Acme Industrial | $1,400,000 | Marcus Webb | Delayed |
No records match this filter.
Jamaica and LLC projects
Same project record collects cost, control and billing. The list above is the earlier sample.
0 selected
| Project ID | Name | Entity | Manager | Phase | Start and End | Budget | Progress | Status | |
|---|---|---|---|---|---|---|---|---|---|
| PRJ-14 | Mandeville Fiber Rollout — Phase 2 | Seiretsu Jamaica | OR Omar Reid | Build | 01 Mar 2026 – 30 Nov 2026 | JMD 100,000,000 | 54% | Active | |
| PRJ-18 | Portmore Estates Installations | Seiretsu Jamaica | MB Marcia Bennett | Install | 01 Jun 2026 – 15 Dec 2026 | JMD 18,000,000 | 48% | Active | |
| PRJ-22 | Kingston Head-End Upgrade | Seiretsu Jamaica | DC Damian Clarke | Commission | 01 Feb 2026 – 20 Oct 2026 | JMD 24,000,000 | 100% | Active | |
| PRJ-26 | Montego Bay POP Battery Replacement | Seiretsu Jamaica | LC Leroy Campbell | Stopped | 01 Apr 2026 – 30 Sep 2026 | JMD 8,000,000 | 70% | Stopped | |
| PRJ-30 | MVNO eSIM Platform Launch | Seiretsu LLC | AP Andre Powell | Build | 01 May 2026 – 31 Jan 2027 | USD 2,400,000 | 36% | Active | |
| PRJ-33 | Ocho Rios Spur | Seiretsu Jamaica | DM Devon McKenzie | Stopped | 01 Jul 2026 – 30 Nov 2026 | JMD 5,000,000 | 62% | Stopped |
No records match this filter.
Planning & Budgeting carries the same project figures in the planning model. Internal Orders hold the capital-project orders.
WBS
1.1.2 starts the day after 1.1.1. 1.2 starts the day after 1.1.
| WBS Code | Name | Type | Start | End | Duration | Predecessors | Baseline Variance | Schedule |
|---|---|---|---|---|---|---|---|---|
| 1 | Mandeville Fiber Rollout — Phase 2 | Phase | 01 Mar 2026 | 15 Nov 2026 | 275 d | — | 0 On Track | |
| 1.1 | Civil | Phase | 01 Mar 2026 | 30 Apr 2026 | 61 d | — | 0 On Track | |
| 1.1.1 | Survey | Task | 01 Mar 2026 | 14 Mar 2026 | 14 d | — | 0 On Track | |
| 1.1.2 | Trench Mandeville Road | Task | 15 Mar 2026 | 30 Apr 2026 | 47 d | 1.1.1 | 0 On Track | |
| 1.2 | Splice and test | Phase | 01 May 2026 | 15 Aug 2026 | 123 d | 1.1 | −6 Ahead | |
| 1.2.1 | Splice Mandeville cabinets | Task | 01 May 2026 | 24 Jun 2026 | 61 d | 1.1.2 | −6 Ahead | |
| 1.3 | Ready for light | Milestone | 01 Sep 2026 | 01 Sep 2026 | 0 d | 1.2 | −14 Ahead |
WBS
1.1.2 starts the day after 1.1.1. 1.2 starts the day after 1.1.
| WBS Code | Name | Type | Start | End | Duration | Predecessors | Baseline Variance | Schedule |
|---|---|---|---|---|---|---|---|---|
| 1 | Mandeville Fiber Rollout — Phase 2 | Phase | 01 Mar 2026 | 30 Nov 2026 | 275 d | — | 0 On Track | |
| 1.1 | Civil | Phase | 01 Mar 2026 | 30 Apr 2026 | 61 d | — | 0 On Track | |
| 1.1.1 | Survey | Task | 01 Mar 2026 | 14 Mar 2026 | 14 d | — | 0 On Track | |
| 1.1.2 | Trench Mandeville Road | Task | 15 Mar 2026 | 30 Apr 2026 | 47 d | 1.1.1 | 0 On Track | |
| 1.2 | Splice and test | Phase | 01 May 2026 | 31 Aug 2026 | 123 d | 1.1 | 0 On Track | |
| 1.2.1 | Splice Mandeville cabinets | Task | 01 May 2026 | 30 Jun 2026 | 61 d | 1.1.2 | 0 On Track | |
| 1.3 | Ready for light | Milestone | 15 Sep 2026 | 15 Sep 2026 | 0 d | 1.2 | 0 On Track |
WBS
1.1.2 starts the day after 1.1.1. 1.2 starts the day after 1.1.
| WBS Code | Name | Type | Start | End | Duration | Predecessors | Baseline Variance | Schedule |
|---|---|---|---|---|---|---|---|---|
| 1 | Mandeville Fiber Rollout — Phase 2 | Phase | 01 Mar 2026 | 12 Dec 2026 | 275 d | — | 0 On Track | |
| 1.1 | Civil | Phase | 01 Mar 2026 | 30 Apr 2026 | 61 d | — | 0 On Track | |
| 1.1.1 | Survey | Task | 01 Mar 2026 | 14 Mar 2026 | 14 d | — | 0 On Track | |
| 1.1.2 | Trench Mandeville Road | Task | 15 Mar 2026 | 30 Apr 2026 | 47 d | 1.1.1 | 0 On Track | |
| 1.2 | Splice and test | Phase | 01 May 2026 | 06 Sep 2026 | 123 d | 1.1 | +6 Behind | |
| 1.2.1 | Splice Mandeville cabinets | Task | 01 May 2026 | 06 Jul 2026 | 61 d | 1.1.2 | +6 Behind | |
| 1.3 | Ready for light | Milestone | 21 Sep 2026 | 21 Sep 2026 | 0 d | 1.2 | +6 Behind |
PRJ-14 by cost type
Budget sums to JMD 100,000,000. Actual sums to JMD 58,000,000. Forecast sums to the earned-value estimate at completion, JMD 107,500,000.
| Cost Type | Budget | Committed | Actual | Forecast | Variance |
|---|---|---|---|---|---|
| Labour | JMD 42,000,000 | JMD 18,000,000 | JMD 24,000,000 | JMD 46,000,000 | − JMD 4,000,000 |
| Contractor | JMD 18,000,000 | JMD 8,000,000 | JMD 10,000,000 | JMD 19,000,000 | − JMD 1,000,000 |
| Materials | JMD 22,000,000 | JMD 9,000,000 | JMD 14,000,000 | JMD 24,000,000 | − JMD 2,000,000 |
| Equipment | JMD 10,000,000 | JMD 4,000,000 | JMD 6,000,000 | JMD 10,500,000 | − JMD 500,000 |
| Travel | JMD 3,000,000 | JMD 1,000,000 | JMD 2,000,000 | JMD 3,000,000 | JMD 0 |
| Other | JMD 5,000,000 | JMD 2,000,000 | JMD 2,000,000 | JMD 5,000,000 | JMD 0 |
| Total | JMD 100,000,000 | JMD 42,000,000 | JMD 58,000,000 | JMD 107,500,000 | − JMD 7,500,000 |
No records match this filter.
Stacked summary
Budget JMD 100,000,000.
Funding limits
Consumed is committed plus actual. PRJ-14 is JMD 42,000,000 + 58,000,000 = JMD 100,000,000, which is 71% of JMD 140,000,000. PRJ-26 is JMD 2,200,000 + 6,400,000 = JMD 8,600,000 against JMD 8,000,000.
| Project | Funding Limit | Cap | Consumed | State |
|---|---|---|---|---|
| PRJ-14 | JMD 140,000,000 | Hard | 71% | OK |
| PRJ-18 | JMD 20,000,000 | Soft | 94% | Warning |
| PRJ-26 | JMD 8,000,000 | Hard | 108% | Breached Work stopped automatically — hard cap reached |
| PRJ-33 | JMD 5,000,000 | Hard | 110% | Breached |
No records match this filter.
Stopped on PRJ-26
The hard cap stopped these items.
Splice crew for 12 Oct
StoppedBattery purchase PO-2260
StoppedTemplates
| Template ID | Name | Phases | Tasks | Last Used | Used By |
|---|---|---|---|---|---|
| TPL-01 | FTTx Neighbourhood Rollout | 4 | 28 | 12 Aug 2026 | 6 |
| TPL-02 | POP Upgrade | 3 | 16 | 02 Sep 2026 | 4 |
| TPL-03 | Business Customer Fiber Installation | 3 | 12 | 20 Sep 2026 | 9 |
No records match this filter.
Recently created
Instantiate adds a row here.
| Project | Template | Manager | Status |
|---|
No records match this filter.
BudgetJMD 100,000,000
ScheduleCurrent finish 12 Dec 2026, 6 days behind Baseline 2